Capital Plan Budget

The capital plan is guided by Policy 3170 which requires a specific multi-year capital plan covering a minimum of three years, and a rolling long-term maintenance and repair plan covering ten years. The purpose of the plan is to identify and prioritize needs of the built environment to further the mission of the school district. This includes deferred maintenance and replacement of existing systems, as well as larger capital improvement projects that support the MPS strategic plan. 

The capital plan is a living document that is reviewed and updated annually and establishes timelines for completion of projects. It also identifies funding sources to support the capital plan include general obligation bonds, long-term facilities maintenance revenue, and capital levies. The focus of the plan continues to be centered around student well-being and academic achievement, including safe and welcoming  entrances, building cooling, athletics and the student dining experience.

Funding Type Amount
General Obligation Bonds $38,099,000
Long-Term Facilities Maintenance Plan $52,237,000
Capital Plan Total $90,336,000
Location Project FY27 FY28 FY29
Field Building Cooling
$12,640,000
Franklin Safe & Welcoming Entrance $1,000,000 $4,900,000
Howe Safe & Welcoming Entrance $1,000,000 $4,045,000
Kenwood Building Cooling
$10,640,000
Kenwood Safe & Welcoming Entrance
$6,340,000
Multi-Site Furniture, Fixtures & Equipment $900,000 $900,000 $900,000
Multi-Site Small Capital Projects $1,500,000 $1,500,000 $1,500,000
Multi-Site Title IX Compliance $1,500,000
Multi-Site Strategic Direction / Transformation $3,000,000 $2,500,000
Multi-Site Security Camera Renewal $1,400,000 $1,000,000 $1,000,000
Multi-Site Playground Improvements $1,500,000 $1,500,000 $1,500,000
Maintenance & Operations Self-Performed Improvements $4,000,000 $4,000,000 $4,000,000
Maintenance & Operations Fleet & Equipment $250,000 $250,000 $250,000
Northrop Building Cooling $10,680,000
Southwest Turf Athletic Field $9,369,000
Student Placement Davis Center Entrance & Security Improvements $500,000
Transportation Fleet Vehicles $1,500,000 $1,500,000 $1,500,000
General Obligation Bonds Subtotal $38,099,000 $32,735,000 $29,630,000
Location Project FY27 FY28 FY29
Multi-Site Building Envelope $5,223,700 $5,626,900 $5,768,200
Multi-Site Hardware & Equipment $2,611,850 $2,813,450 $2,884,100
Multi-Site Electrical Systems $2,611,850 $2,813,450 $2,884,100
Multi-Site Interior Surfaces $7,835,550 $8,440,350 $8,652,300
Multi-Site Mechanical Systems $18,282,950 $19,694,150 $20,188,700
Multi-Site Plumbing Systems $3,917,775 $4,220,175 $4,326,150
Multi-Site Professional Services $3,917,775 $4,220,175 $4,326,150
Multi-Site Roof Systems $5,223,700 $5,626,900 $5,768,200
Multi-Site Site Projects $2,611,850 $2,813,450 $2,884,100
LTFM Bonds Subtotal $52,237,000 $56,269,000 $57,682,000